Ilocos Norte Police Attributes Peaceful Polls To Voters’ Cooperation

Pinuri ng INPPO ang mga botante sa kanilang kooperasyon na nagresulta sa mapayapang halalan sa Ilocos Norte.

PCG-5 Facilitates 80K Passengers In Bicol Ports During Poll Period

Naging matagumpay ang Philippine Coast Guard sa Bicol sa pag-facilitate ng 80,000 pasahero sa kanilang mga pantalan nitong Mayo 9 hanggang 12.

Group Urges Candidates To Help Remove Campaign Materials

Nagsagawa ang isang grupo ng cleanup matapos ang halalan, hinihimok ang mga kandidato na maging responsable sa kanilang mga campaign materials.

TESDA To Assess Almost 1K OFWs In Jeddah, Riyadh

970 OFWs sa Jeddah at Riyadh ang nakakuha ng pagkakataon para sa libreng competency assessment mula sa TESDA. Isang magandang tulong ito.

NLEX Connector Road Project, 45% Complete: DPWH

The Department of Public and Highways reported that the eight-kilometer North Luzon Expressway-South Luzon Expressway (NLEX-SLEX) Connector Road Project is 45 percent complete.

NLEX Connector Road Project, 45% Complete: DPWH

12
12

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Department of Public and Highways (DPWH) on Wednesday reported that the eight-kilometer North Luzon Expressway-South Luzon Expressway (NLEX-SLEX) Connector Road Project is 45 percent complete.

Upon completion, it will extend NLEX southward from Segment 10 to Skyway Stage 3.

DPWH Senior Undersecretary Rafael Yabut representing Acting Secretary Roger Mercado, led the inspection of the ongoing construction of the second section of NLEX Connector at España, Manila.

He said the concessionaire, Manila North Tollways Corporation (MNTC) reported that the project, is now almost halfway-finished with civil works, which will serve as the first connector toll road for all vehicles including heavy trucks.

Also, Section 1 which is the 5.15-kilometer segment from C3, Caloocan to España, Manila is now 64.5 percent complete while the 2.75-kilometer Section 2 from España, Manila to PUP Sta. Mesa, Manila is now 3.1 percent complete.

When completed, the elevated road will reduce travel time from SLEX to NLEX to just 20 minutes and benefit at least 35,000 motorists/vehicles per day.

Using the four-lane toll road, travel time from Clark to Calamba will be reduced from approximately three hours to one hour and 40 minutes.

The project inspection was also attended by DPWH Undersecretary Maria Catalina Cabral, Assistant Secretary Wilfredo Mallari, Director Constante Llanes Jr., Director Alex Bote, and officials of the NLEX Corporation.

The NLEX-SLEX Connector Road Project which costs PHP23.2 billion began construction in May 2019.

The multi-billion peso project is expected to be opened by the third quarter of 2023. (PNA)