DSWD-Calabarzon Disburses PHP5.13 Billion In Crisis Aid In 2024

Tulong mula sa DSWD-Calabarzon, PHP5.13 bilyon na ipinamahagi sa mga nangangailangan sa ilalim ng Crisis Intervention Program.

Over 100 Bicol Cops Recognized For Outstanding Service

Ang 101 na pulis sa Bicol ay pinarangalan sa kanilang natatanging kontribusyon. Isang hakbang patungo sa mas maayos na komunidad.

PNP Deploys 37K Cops For New Year Security Nationwide

Sa pagdiriwang ng Bagong Taon, 37,000 pulis ang naitalaga ng PNP para sa seguridad at kaayusan.

Philippine Posts One Of Highest Economic Growth In Asia In 2024

Kahit sa gitna ng tensyon, patuloy na lumalago ang ekonomiya ng Pilipinas. Isang magandang balita para sa bayan.

Completion Of GenSan Airport Terminal Project Faces Slight Delay

The slight delay is due to the COVID-19 pandemic.
By The Luzon Daily

Completion Of GenSan Airport Terminal Project Faces Slight Delay

6
6

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The completion of the PHP452 million new passenger terminal building of the city international airport here is facing another slight delay due to the coronavirus disease 2019 (Covid-19) pandemic.

Edgardo Cueto, manager of the Civil Aviation Authority of the Philippines (CAAP) here, said Tuesday installation of the remaining facilities of the terminal building has been stretched until September due to the late arrival of commissioned workers from Indonesia.

He said materials for the passenger boarding bridge have already arrived but it will be installed by the Indonesian supplier.

Once the workers arrive, he said they are still required to undergo mandatory quarantine for 21 days based on the protocol set by the city government.

“Hopefully the remaining components will be installed before the end of September,” he said in an interview.

Cueto said the expansion and rehabilitation of the main airport passenger terminal building are now 85 to 87 percent complete.

He said joint venture firms Vicente T. Lao Construction and C.B. Garay Philwide Builders Inc. have been working double-time to complete the project, which was previously set last May.

The construction works were partially disrupted in March due to the Covid-19 pandemic but later resumed in full swing, with the temporary closure of the city airport to commercial passenger flights.

Cueto said they cannot say yet as to when the new airport terminal will become fully operational.

“Rest assured that we are regularly monitoring its progress and necessary adjustments are being made to fast-track the process,” he said.

The airport terminal project, which started in June 2017, was part of the PHP959-million funding approved by the Department of Transportation in 2015 for the upgrading and improvement of the city airport.

It was originally targeted for completion in June last year.

The project includes the expansion of the airport’s terminal building’s arrival and pre-departure area and the improvement of basic facilities; upgrading of water supply facilities; upgrading of navigational aids; and improvement of various support facilities, including its power plant. (PNA)